Preliminary Project Plan and Schedule for Dam Reconstruction

PROJECT PLAN & SCHEDULE

JANURAY, 2005
PRE-APPLICATION PHASE & CONCEPTUAL DESIGN 4 MONTHS
START MID-JANUARY2005
SUBMIT FOR APPROVAL MAY 1, 2005

JULY, 2005
DEP APPROVALS RECEIVE APPROVAL JULY 1, 2005 2 MONTHS

* AUTHORIZATION TO PROCEED IN MID-JANUARY
* HYDROLOGIC/HYDRAULIC WATERSHED EVALUATION
* DAM BREACH ANALYSIS
* RE-EVALUATION OF THE DAM HAZARD CLASSIFICATION
* CONCEPTUAL DRAWINGS OF THE DAM

JULY, 2005
APPLICATION PHASE 12 MONTHS
START JULY 1, 2005
SUBMIT FOR APPROVAL JULY 1, 2006

JULY, 2006
DEP – PINELANDS APPROVALS 3 MONTHS

RECEIVE APPROVAL OCTOBER 1, 2006 (FOLLOWING SUBMISSION)
* AUTHORIZATION TO PROCEED
* SITE SURVEY & GEOTECHNICAL INVESTIGATION
* ARCHEOLOGICAL STUDY
* STRUCTURE & HYDRAULIC PRELIMINARY DESIGN
* ENVIRONMENTAL IMPACT STATEMENT
* FINAL DESIGN DRAWINGS & SPECIFICATIONS
* EMERGENCY ACTION PLAN
* OPERATIONS & MAINTENANCE MANUAL
* CONSTRUCTION COST & TIME ESTIMATE

OCTOBER, 2006
BID & AWARD 2 MONTHS

DECEMBER, 2006
BEGIN CONSTRUCTION 18 MONTHS

JUNE 1, 2008
PROJECT COMPLETED